All Posts Tagged Tag: ‘Ellerbe Becket’

Insurance Data Center

Owner: Insurance Company
Architect:
Engineer: Ellerbe Beckett
General Contractor: Holder Construction
Division: Data Centers
Category: Computer Centers
Region: Arizona
Electrical Construction Cost: $12,000,000.00
Completion: 1997

Select a tag from the list below to see similar projects.

Insurance Data Center

Owner: Insurance Company
Architect:
Engineer: Ellerbe Beckett
General Contractor: Holder Construction
Division: Data Centers
Category: Computer Centers
Region: Texas
Electrical Construction Cost: $12,000,000.00
Completion: 1998

Select a tag from the list below to see similar projects.

Insurance Data Center

Owner: Insurance Company
Architect: Ellerbe Beckett
Engineer: Ellerbe Beckett
General Contractor: Holder Construction
Division: Data Centers
Category: Computer Centers
Region: Georgia
Electrical Construction Cost: $19,250,000.00
Completion: October 1996

Select a tag from the list below to see similar projects.

Corporate Insurance Data Center and Headquarters

Owner: Insurance Company
Architect:
Engineer: Ellerbe Becket
General Contractor: Holder Construction
Division: Data Centers
Category: Computer Centers
Region: Illinois
Electrical Construction Cost: $32,000,000.00
Completion: 2001

Select a tag from the list below to see similar projects.

OptiGlobe Data Center

Owner: OptiGlobe
Architect: Ellerbe Beckett
Engineer: Ellerbe Beckett
General Contractor: Racional, Holder Construction
Division: Data Centers
Category: Computer Centers
Region: Sao Paulo, Rio de Janerio, Buenos Aires
Electrical Construction Cost: $25,620,000.00 for all three facilities
Completion: Sao Paulo – November 2000,
Rio de Janerio – May 2001, and
Buenos Aires – June 2001

Select a tag from the list below to see similar projects.

E*Trade Data Center

Owner: E*Trade
Architect: Ellerbe Becket
Engineer: Ellerbe Becket
General Contractor: Holder Construction
Division: Data Centers
Category: Computer Centers
Region: Georgia
Electrical Construction Cost: $22,000,000.00
Completion: 1998

Select a tag from the list below to see similar projects.

West Georgia Medical Center

Owner: West Georgia Medical
Architect: Ellerbe Becket
Engineer: Ellerbe Becket
General Contractor: McCarthy
Division: Healthcare, Low Voltage/Telecommunication Cabling
Category: Hospitals, Fire Alarm Systems
Region: LaGrange, GA
Electrical Construction Cost: $6,400,000.00
Completion: August 2010

Select a tag from the list below to see similar projects.

Turner Field

Owner: Atlanta Fulton County Recreation Authority
Architect: Heery International, Rosser International, Williams Russell Johnson, Ellerbe Beckett
Engineer: Rosser International
General Contractor: Beers Construction Company, H.J. Russell Company, C.D. Moody
Division: Sports & Entertainment, Low Voltage/ Telecommunication Cabling
Category: Sports Facilities, Fire Alarm, Grounding/ Bonding Systems
Region: Atlanta, GA
Electrical Construction Cost: $3,300,000.00
Completion: March 1997
Additional Comments Converted from 1996 Centennial Olympic Stadium

Select a tag from the list below to see similar projects.

Centennial Olympic Stadium

Owner: Atlanta Fulton County Recreation Authority
Architect: Heery International, Rosser International, Williams Russell Johnson, Ellerbe Beckett
Engineer: Rosser International
General Contractor: Beers Construction Company, H.J. Russell Company, C.D. Moody
Division: Sports & Entertainment, Low Voltage/ Telecommunication Cabling
Category: Sports Facilities, Fire Alarm, Grounding/ Bonding Systems
Region: Atlanta, GA
Electrical Construction Cost: $11,000,000.00
Completion: 1996

Select a tag from the list below to see similar projects.