All Posts Tagged Tag: ‘Paging Systems’

Northside Cherokee Replacement Hospital

Owner: Northside Cherokee Replacement Hospital
Architect: HDR and Howell Rusk Dodson
Engineer: HDR
General Contractor: Batson-Cook Company
Division: Healthcare, Low Voltage/Telecommunication Cabling
Category: Central Energy Plants, Hospitals, Radiology Centers, Surgical Centers, Women’s Centers, CATV Systems, CCTV Systems, Fire Alarm Systems, Grounding and Bonding Systems, Nurse Call Systems, Paging Systems, Security Systems
Region: Canton, GA
Electrical Construction Cost: $24,250,000.00 Electrical & Low Voltage
Completion: May 2017

Select a tag from the list below to see similar projects.

The Lovett School Murray Athletic Center

Owner: The Lovett School
Architect: Collins Cooper Carusi
Engineer: NBP
General Contractor: Brasfield & Gorrie
Division: Higher Education, Sports & Entertainment, Low Voltage/Telecommunication Cabling
Category: Private School Facilities, Sports Facilities, Fire Alarm Systems, Grounding and Bonding Systems, Multimode and Singlemode Fiber, Network Distribution Cable, Paging Systems, Structured Cabling
Region: Atlanta, GA
Electrical Construction Cost: $1,500,000.00 Electrical & Low Voltage
Completion: December 2016

Select a tag from the list below to see similar projects.

Northside Hospital – Forsyth Vertical Addition

Owner: Northside Hospital
Architect: Howell Rusk Dodson
Engineer: EXP
General Contractor: Batson-Cook Company
Division: Healthcare, Low Voltage/Telecommunication Cabling
Category: Hospitals, Fire Alarm Systems, Nurse Call Systems, Paging Systems
Region: Cumming, GA
Electrical Construction Cost: $2,800,000.00 Electrical
Completion: October 2016

Select a tag from the list below to see similar projects.

WellStar – East Cobb Health Park

Owner: WellStar
Architect: CDH Partners
Engineer: Perry Crabb & Associates, Inglett & Stubbs
General Contractor: Brasfield & Gorrie
Division: Healthcare, Low Voltage/Telecommunication Cabling
Category: Medical Office Buildings, Radiology Centers, CATV Systems, CCTV Systems, Distributed Antenna Systems, Fire Alarm Systems, Grounding and Bonding Systems, Multimode and Singlemode Fiber, Network Distribution Cable, Nurse Call Systems, Outside Plant Cabling, Paging Systems, Security Systems, Structured Cabling
Region: Marietta, GA
Electrical Construction Cost: $4,500,000.00 Electrical & $1,400,000.00 Low Voltage
Completion: September 2014

Select a tag from the list below to see similar projects.

Floyd – Polk Medical Center

Owner: Floyd-Polk Medical
Architect: Earl Swenson
Engineer: Phoenix, GBA
General Contractor: Brasfield & Gorrie
Division: Healthcare, Low Voltage/Telecommunication Cabling
Category: Hospitals, CATV Systems, CCTV Systems, Distributed Antenna Systems, Fire Alarm Systems, Grounding and Bonding Systems, Multimode and Singlemode Fiber, Network Distribution Cable, Nurse Call Systems, Outside Plant Cabling, Paging Systems, Security Systems, Structured Cabling
Region: Cedartown, GA
Electrical Construction Cost: $3,250,000.00 Electrical & $950,000.00 Low Voltage
Completion: October 2014

Select a tag from the list below to see similar projects.

WellStar – Paulding Hospital

Owner: WellStar
Architect: CDH Partners
Engineer: Perry Crabb & Associates, J&A Engineering
General Contractor: Brasfield & Gorrie
Division: Healthcare, Low Voltage/Telecommunication Cabling
Category: Hospitals, CATV Systems, CCTV Systems, Distributed Antenna Systems, Fire Alarm Systems, Grounding and Bonding Systems, Multimode and Singlemode Fiber, Network Distribution Cable, Nurse Call Systems, Outside Plant Cabling, Paging Systems, Security Systems, Structured Cabling
Region: Hiram, GA
Electrical Construction Cost: $11,500,000.00 Electrical & $2,500,000.00 Low Voltage
Completion: April 2014

Select a tag from the list below to see similar projects.

WellStar – Kennestone Hospital Women’s Center

Owner: WellStar
Architect: CDH Partners
Engineer: Perry Crabb & Associates
General Contractor: Brasfield & Gorrie
Division: Healthcare, Low Voltage/Telecommunication Cabling
Category: Hospitals, Women’s Centers, CATV Systems, CCTV Systems, Fire Alarm Systems, Grounding and Bonding Systems, Multimode and Singlemode Fiber, Network Distribution Cable, Outside Plant Cabling, Paging Systems, Security Systems
Region: Marietta, GA
Electrical Construction Cost: $3,500,000.00
Completion: 2004

Select a tag from the list below to see similar projects.

Northside Hospital – Forsyth Women’s Center

Owner: Northside Hospital
Architect: Howell Rusk Dodson
Engineer: Perry Crabb & Associates
General Contractor: Batson-Cook
Division: Healthcare, Low Voltage/Telecommunication Cabling
Category: Hospitals, Women’s Centers, Fire Alarm Systems, Nurse Call Systems, Paging Systems
Region: Cumming, GA
Electrical Construction Cost: $4,100,000.00 Electrical & Low Voltage
Completion: September 2008
Additional Comments Women Center Addition $1,900,000.00 in September 2011

Select a tag from the list below to see similar projects.

WellStar – Kennestone Outpatient Pavilion

Owner: WellStar and Meadows & Ohly
Architect: Archimages
Engineer: Perry Crabb & Associates, HPD, J&A Engineering
General Contractor: Brasfield & Gorrie
Division: Healthcare, Low Voltage/Telecommunication Cabling
Category: Medical Office Buildings, Surgical Centers, Radiology Centers, CATV Systems, CCTV Systems, Fire Alarm Systems, Grounding and Bonding Systems, Multimode and Singlemode Fiber, Network Distribution Cable, Outside Plant Cabling, Paging Systems, Security Systems
Region: Kennesaw, GA
Electrical Construction Cost: $4,300,000.00
Completion: December 2011

Select a tag from the list below to see similar projects.

WellStar – Acworth Health Park

Owner: WellStar
Architect: CDH Partners
Engineer: Perry Crabb & Associates, J&A Engineering
General Contractor: Brasfield & Gorrie
Division: Healthcare, Low Voltage/Telecommunication Cabling
Category: Medical Office Buildings, Radiology Centers, CATV Systems, CCTV Systems, Fire Alarm Systems, Grounding and Bonding Systems, Multimode and Singlemode Fiber, Network Distribution Cable, Outside Plant Cabling, Paging Systems, Security Systems
Region: Acworth, GA
Electrical Construction Cost: $1,900,000.00 Electrical & $600,000.00 Low Voltage
Completion: June 2012

Select a tag from the list below to see similar projects.

Page 1 of 212»